Architekwiki
  • Home
  • WIKI
  • Start Here
  • Resources
  • Subscribe
  • Other
    • Reading List
    • Ochre >
      • Ochre
      • Ochre KB
      • Ochre FAQs
      • Ochre Help
    • Details
    • The 3 Aspects
    • About
    • Terms of Use
  • Home
  • WIKI
  • Start Here
  • Resources
  • Subscribe
  • Other
    • Reading List
    • Ochre >
      • Ochre
      • Ochre KB
      • Ochre FAQs
      • Ochre Help
    • Details
    • The 3 Aspects
    • About
    • Terms of Use

Architekwiki

A Resource For Architects
Click here to get good stuff in your inbox

Spec Writing

8/29/2020

 
Spec Writing
One size does NOT fit all like I was taught.

My first job after college was with a firm that designed public schools. There was always a full project manual to accompany the drawings. My summer job experience was similar. There was always a project manual.

Ten years out of school I started my own firm. I always developed a full project manual. After two or three years an occasional exception appeared. We did a few projects for contractors who were acting as design/builders.

But as a rule if the client was the "Owner" and there was any kind of bidding, I produced a project manual.​

Thinking back on that era, I realize now that a major factor in having a project manual was that there wasn’t really an alternative.

Now computers can place lots of text on the drawings and it isn’t hard to do. You can put whole specs right on the drawings, or wordy keynotes.

It is embarrassing how long it took for the thought to occur that a project manual was overkill for most projects. Some clues were that you never saw anyone using the specs to get the project built. Often I had to provide an extra copy if I wanted one handy in the contractor’s job-site trailer.

I sometimes like to use math to tell me if I am trying to do the impossible. I discovered how helpful that can be when nothing seems to work. Once, I was struggling to fit a building with parking on a piece of land in a reasonable arrangement. I did some math after days of schemes that fell short.

I learned that the trapezoidal shape of the lot, minus required setbacks was only 2,000 SF larger than the sum of building and parking. The good news was it could work. The bad news was that the parking had to be ultra efficient and the building had to have stepped side walls to mimic the trapezoid.

When it comes to project manuals, here is what the math tells me. A realistic allowance of 40+ hours to produce a project manual is just not in the design budget for most projects that small firm architects encounter.

I did the Specifications math here.

The solution is to find a drawing-based process that works for you on nearly every project. The spec-writer middle man has to go. ​

I will explain the process that I used to give you an example of what I mean. First my process wasn’t static because we had a wide range of projects. So one of these situations should come close to what you do.
Spec Writing
.The process changes as it gets bigger and more public. Bigger projects are often more complicated, and public projects have more ‘must do’ requirements.

The graphic shows my solution to each situation. Here is what I mean by the terms.

Notes
Notes are detailed notes placed where required on the drawings that tie down the materials that are required. So, for instance, a concrete sidewalk note might read, “5” PLAIN 3500 PSI CONC WITH 6% AIR-ENTRAINMENT. PLACE CONTRACTION JTS @ 5’ OC AND EXP JTS @ 25’ OC.

Bid Form
A Bid Form is two to four pages long and briefly describes the project, when and where bids are due, and the form required of the bid submittal including listing any other submissions required, such as, proof of insurance, bonds, etc. This document would be emailed to invited contractors.

SpecNotes
SpecNotes are detailed notes placed as a group on the drawings and referenced by their ID Number on plans and details, similar to keynotes. The SpecNotes ARE the specification and include General Requirements. You can learn more about SpecNotes here.

Front End Spec
A Front End Spec is an abbreviated Project Manual and contains just the legal stuff:
  • An Invitation To Bid
  • Bid Instructions
  • Bid Form
  • Form Of Contract
  • General Conditions Of The Contract
  • General Requirements (Div 1)

Bid Docs
Bidding Documents are similar to a Front End Spec, but contain just the documents related to bidding. Once a contract is signed, these documents are no longer in effect. Bid Docs contain the  Advertisement For Bid, Instructions To Bidders, Bid Form.

Project Manual
The Project Manual is the book of “Front End Specs” and all the technical specs that you find in systems like SpecLink+, eLink, MasterSpec and others. The difference here is that I used the Project Manual to provide the 'Part 1 - General' and 'Part 3 - Execution' of the CSI spec format. The 'Part 2 - Products' information is covered by the SpecNotes so that portion of each spec simply says, “See the drawings for the type and extent of products required.”

As you can see I nearly always used SpecNotes. My experience has been that contractors are much more likely to give you what you want if it is on the drawings. If critical information is only found in the Project Manual, you will need to be much more vigilant about what is actually provided.

In addition, by having everything that’s critical on the drawings it is much easier to coordinate and verify - not to mention MUCH easier to edit your master SpecNotes than assemble an entire Project Manual.

This approach is the only way that I can think of where you could develop your own master Project Manual that only requires updated headers for each job. The holy grail for me was just that. Select the spec sections that are needed and assemble them for distribution. Or better yet - eliminate the Project Manual altogether.
Rick Wolnitzek

Comments are closed.
    Resources

    Start Here

    YouTube Channel

    Picture

    Picture

    Terms of Use
    Your use of Architekwiki is implicit agreement with the 
    ​
    Terms of Use.
    x
    Get Good Stuff in Your Inbox
    Picture
    Subscribe

    Archives

    September 2023
    July 2023
    April 2023
    March 2023
    February 2023
    January 2023
    November 2022
    October 2022
    July 2022
    June 2022
    April 2022
    October 2021
    September 2021
    August 2021
    June 2021
    May 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    December 2018
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    October 2017
    September 2017
    August 2017
    July 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    December 2016
    November 2016
    October 2016
    September 2016
    August 2016
    July 2016
    June 2016
    May 2016
    April 2016
    March 2016
    February 2016
    January 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015
    June 2015
    May 2015
    April 2015
    March 2015
    February 2015
    January 2015
    December 2014
    November 2014
    October 2014
    September 2014
    August 2014
    July 2014
    June 2014
    May 2014
    April 2014
    March 2014
    February 2014
    January 2014
    December 2013
    November 2013
    October 2013
    September 2013
    August 2013
    July 2013
    June 2013
    May 2013
    April 2013
    March 2013
    February 2013
    January 2013
    December 2012
    November 2012
    October 2012

    Categories

    All
    Business Development
    Business Management
    Design
    Detail
    Miscellaneous
    Project Management
    Resources

Picture

Picture
VISIT ARCHITEKWIKI'S RESOURCES
​
START HERE
ABOUT
SIGN UP
TERMS OF USE
Architekwiki | Architect's Resource | Greater Cincinnati 
© 2012-2022   Architekwiki​